Tanks for the memory!

(Post title given by our central heating expert, Dave!!)When we arrived at St Mark’s, we found there were two boilers, one of which is located in the children’s room. There was also a water tank there that was very high up. One of the jobs today was to...

Carpet fitting

The carpet in the foyer was fitted today. The carpet for the main hall has to be bound first before it can be fitted, to prevent fraying. Our thanks go to the carpet fitters!

Progress in other rooms too!

And just so the other rooms don’t feel left out…!Work is going on preparing for additional electrics to be put in the community hall:… even though Garry and Mark don’t appear to be talking!Blinds were fitted in the community hall as well:A new...

Progress in the main hall

There is ongoing progress in the main hall, and more to come!This week we’ve seen the floor varnished again:The carpet tiles from the foyer were removed in preparation for the new carpet being fitted there:Blinds have been fitted. These were needed because the...

On windows…

On Tuesday 25th May, new windows were fitted in the main hall. The difference this has made to the appearance of that room is remarkable! This is what the windows in the main hall looked like.Here, the fitters are removing the old windows.No glass in… no windows...